Micro Hydro Scheme Scotland Case Study: Larichfraskan

Proterra Energy carried out the feasibility, design and installation of the Larichfraskan micro hydro scheme in 2015.

Considering the head and flow availability on site, a Turgo turbine was identified as the best option and the scheme was sized at 15kW. 

 

With an 80% load factor, the scheme continues to provide a reliable and secure source of power for the local property, off-setting the majority of the electricity use while exporting the remaining energy to the national grid.

To see this scheme in action check out our YouTube channel on the link below.

Hydro Scheme Installation, Green Renewable Energy

Larichfraskan Micro Hydro Scheme Specifications

Power:

Turbine:

Head:

Flow:

Location:

Commissioned:

Perthshire

45 l/s

50m

Turgo

15kW

2015