Proterra Energy was employed to carry out the feasibility for a micro hydro scheme on a site in rural Angus.
The site posed several challenges around the construction of the intake and in the laying of the penstock, however through careful planning and design a viable 30kW hydro scheme was proposed.
Installation went ahead in 2018 and the scheme is now operational with all maintenance and monitoring being carried out by Proterra Energy.
Specifications
Common
Power
30kW
Location
Angus
Commissioned
2018
Specific
Turbine
Turgo
Flow
63 l/s
Head
67m
Testimonial
We do not have a testimonial regarding this project. If you need to know more about this project please contact us.
Additional Information
The site posed several challenges around the construction of the intake and in the laying of the penstock, however through careful planning and design a viable 30kW hydro scheme was proposed.
Installation went ahead in 2018 and the scheme is now operational with all maintenance and monitoring being carried out by Proterra Energy.