Micro Hydro Scheme Scotland Case Study: Larichfraskan

Introduction

Proterra Energy carried out the feasibility, design and installation of the Larichfraskan micro hydro scheme in 2015.

Considering the head and flow availability on site, a Turgo turbine was identified as the best option and the scheme was sized at 15kW.

With an 80% load factor, the scheme continues to provide a reliable and secure source of power for the local property, off-setting the majority of the electricity use while exporting the remaining energy to the national grid.

To see this scheme in action check out our YouTube video.

Specifications

Common

Power

15kW

Location

Perthshire

Commissioned

2015

Specific

Turbine

Turgo

Flow

45 l/s

Head

50m

Testimonial

We do not have a testimonial regarding this project. If you need to know more about this project please contact us.

Additional Information

Considering the head and flow availability on site, a Turgo turbine was identified as the best option and the scheme was sized at 15kW.

With an 80% load factor, the scheme continues to provide a reliable and secure source of power for the local property, off-setting the majority of the electricity use while exporting the remaining energy to the national grid.

To see this scheme in action check out our YouTube video.

Want to know more?

Are you interested in this project?

Quick Enquiry

Get in touch with Proterra Energy directly, or use the form below to request an email or call back and we’ll get in touch as soon as possible.