Micro Hydro Scheme Installation and Maintenance Case Study: Glen Hinnisdal, Isle of Skye

Introduction

Proterra Energy was employed to carry out the feasibility for a micro-hydro scheme in Glen Hinnisdal on Skye.

Due to the incised nature of the burn and considering the elevation head and flow availability, a 15kW scheme was identified as the best option and one that would minimise environmental disturbance. The scheme was built by Proterra Energy and commissioned in 2013.

Due to the steepness of the river course, a turgo turbine was chosen. The turbine house was located discreetly beneath a steep section of waterfalls and given a turf roof to minimise its visual impact. Proterra Energy provides the major maintenance and servicing support for the scheme and it continues to operate efficiently and produce high yields.

Specifications

Common

Power

15kW

Location

Glen Hinnisdal, Skye

Commissioned

2013

Specific

Turbine

Turgo

Flow

46 l/s

Head

50m

Testimonial

We do not have a testimonial regarding this project. If you need to know more about this project please contact us.

Additional Information

Due to the incised nature of the burn and considering the elevation head and flow availability, a 15kW scheme was identified as the best option and one that would minimise environmental disturbance. The scheme was built by Proterra Energy and commissioned in 2013.

Due to the steepness of the river course, a turgo turbine was chosen. The turbine house was located discreetly beneath a steep section of waterfalls and given a turf roof to minimise its visual impact. Proterra Energy provides the major maintenance and servicing support for the scheme and it continues to operate efficiently and produce high yields.

Want to know more?

Are you interested in this project?

Quick Enquiry

Get in touch with Proterra Energy directly, or use the form below to request an email or call back and we’ll get in touch as soon as possible.